Works At The Juventus Center According To Plans
The Juventus Center in Vinovo is about to come back to life. After two months from the last training session (30th May, the eve of the match against Lazio), the tea, is nearly ready to get back. It will do so on Wednesday afternoon, once again with Ciro Ferrara at the helm.
The word “works” has been very current recently. At the Juventus head quarters the project has continued: the construction of two stands for the public to watch the training sessions of the first team and the matches of the youth sector as well as the expansion of the dressing rooms area.
Since the last update of the situation at the beginning of July, the works have continued according to plans.
The stand overseeing pitch number 8 – the synthetic one which last year was named after Alessio Ferramosca and Riccardo Neri – is finished and was inspected in the last few days by the inspectorate commission which will issue the permits for use for the start of the youth tournament entitled “Ale&Ricky sempre nel cuore".
The other stand, the one overseeing the number 1 pitch, one on which Del Piero and company do their daily training sessions, is also progressing well. Both the structure and the parking area adjacent to it are nearly completed.
Everything is going according to the time envisaged even for the dressing rooms area. In time for the return of the first team to Vinovo, the works on the ground floor have been completed while the works to the upper floor are moving fast.
The works will continue even when the sport activities begin. The objective remains that of finishing all the works by mid October, as foreseen in the plans.